What capacity should you use when the boom length of the crane falls between the lengths listed in the load chart?

  1. The next longest boom length

  2. The next shortest boom length

  3. A length estimated between the lengths in the chart

  4. The next longest or the next shortest boom length, whichever is the lower capacity

The correct answer is: The next longest or the next shortest boom length, whichever is the lower capacity

When determining the appropriate capacity to use for a crane with a boom length that falls between the lengths listed in the load chart, selecting the next longest or the next shortest boom length, whichever has the lower capacity, is essential for ensuring safety and compliance with operational guidelines. This approach is based on the principle of conservatism in load handling; by choosing the lower capacity, the operator mitigates the risk of overload, which could lead to a failure of the crane or a dangerous situation. In practice, load charts are designed to provide the maximum lifting capacity at specific boom lengths, and it is crucial to adhere to these limits. If a boom length is not explicitly listed, it is common to refer to the capacities of the adjacent lengths to make the safest decision. By choosing the lower capacity between the next longest and the next shortest options, the operator accounts for the potential decreased stability or increased stresses that may arise when using a boom length not directly referenced in the load chart. The other approaches, such as relying solely on the next longest or next shortest without considering their respective capacities, could lead to unsafe lifting practices. Estimating a capacity between the listed values lacks a basis in the established metrics of the load chart, potentially resulting in overloading the crane